Inside the 1936 building

Here are some pictures of the inside of the 1936 building:





















Follow the library construction on Flickr

There are two Flickr accounts where you will find updated pictures of the ongoing construction at the Visalia Library:

VCM - Visalia Library's photos maintained by the project managers Vanir Construction Management, Inc.

Visalia Library Construction maintained by library staff.

Wednesday, July 11, 2007

Library Courtyard Demolition

The courtyard that separates the 1936 building and the 1976 building is demolished. A lobby will be built here connecting the two buildings.


Tuesday, July 3, 2007

Lots of changes

Much has changed in the last couple of weeks:

A giant partition has been erected, closing off the old entrance to the library, including the old Circulation Desk.










The entire south side of the building is fenced off.









The temporary entrance on the north side of the building is being used (notice the shiny new book drops).











And the new circulation desk is now in operation.











Be sure to visit our Flickr account to see the rest of our photos!